Beard Construction, engaged to develop new and existing engineering facilities at Richmond upon Thames College (RuTC), required a dependable temporary power solution. Initially contracted to support building commissioning works, the project scope expanded to include operational power for the college’s engineering department due to delays from a statutory authority. This development reinforced Beard Construction’s confidence in Star Power, establishing the company as their first-choice provider.
A statutory authority delay jeopardised the commissioning of two educational buildings, critical for the new term. This setback necessitated a responsive and reliable temporary power solution to bridge the gap and maintain progress.
Following a detailed site survey, the Star Power team provided a tailored power solution, including:
Oli Kenworthy, Beard Construction: “Matt and his team acted professionally throughout the process of sizing, surveying, and installing the generator here at the RuTC. The quick, responsive nature, in light of a statutory authority letdown, was a real testament to Star Power’s positive and committed attitude. The team on-site is grateful for the service and responsiveness, which enabled the two educational buildings to begin commissioning for the new term.”
Star Power’s responsive and reliable temporary power solutions ensured the successful commissioning and operation of RuTC’s engineering facilities. Beard Construction’s trust in Star Power’s capabilities underscores the effectiveness of this partnership and paves the way for future collaborations.